What to look for in a care home wet room refurbishment
Care home wet room refurbishments that disappoint usually do so for reasons settled before the contractor arrived: a floor finish nobody asked the wet PTV of, a door a hoist cannot get through, a capped-off bath supply left as a dead leg. This guide sets out what to specify, what to ask a contractor, how to run the works with residents at home, and what a proper handover should leave you with. The same points apply to a care home shower room refurbishment and to nursing home bathroom refurbishment, where hoist access and two-person care make them matter even more.
Start the specification from the residents
A wet room is specified from the people who will use it. Before any drawings, write down how residents who use the room bathe and transfer now: standing, seated, in a shower chair, or with a mobile or ceiling hoist and two staff. Then look two to five years ahead. A room designed for a shower chair, a hoist and two carers will still suit a resident who showers independently, but a room designed only for today’s independent residents will need doing again.
That summary should be the first document the contractor sees. If a contractor arrives with a product brochure before asking how your residents move, treat that as information about how the job will be run.
Care home bathroom design: the specification points that decide whether the room works

Floor falls and drainage
The fall to the drain is where a wet room succeeds or fails. Water should run to the drain from the shower area without pooling at the edges and without the gradient becoming something a shower chair rolls down. Ask how the fall will be formed on your floor construction, whether timber or concrete, and where the drain will sit relative to the seat and the carer’s working position.
Slip resistance you can measure
Ask for the wet pendulum test value (PTV) of any floor finish proposed. Using the UK Slip Resistance Group classification that HSE applies, 36 and above is low slip potential, 25 to 35 moderate and 0 to 24 high. The same finish should run across the whole room, not just the shower zone, because water and residents both move around a wet room.
TMVs and water safety
HSE’s position for health and social care is that where vulnerable people are at risk from scalding during whole-body immersion, water temperatures must not exceed 44°C, and baths and showers should be fitted with TMVs. The specification should say which valves, where they sit, and that they will be accessible for testing.
The Legionella side needs the same attention. A refurbishment is the right time to remove redundant pipework and the easiest time to create a new dead leg, usually by capping off a supply that once served a bath. The new outlets should go into your flushing and temperature monitoring regime from the first day of use.
Finishes that support IPC
Regulation 12 and the Code of Practice on the prevention and control of infections set the expectation; the bathroom is where it becomes physical. Look for a continuous, impervious sheet floor with welded seams, coved up the wall. Large-format wall panels with few joints are easier to keep clean than small tiles and a lot of grout. Wall-hung WCs and basins leave the floor clear underneath. Put the proposed finishes in front of your IPC lead before the specification is signed, not after the room is finished.
Space for hoists and carers
A room that looks generous empty can be unworkable with a hoist, a shower chair and two staff inside it. HBN 00-02 is written for NHS buildings, but its assisted shower room layouts are the most useful benchmark available, including space for staff to work from the sides and front of a shower seat. Measure the door’s effective clear width with the hoist and widest shower chair in mind: Approved Document M Volume 2 gives 800mm for a straight-on approach and 825mm for a right-angled approach from a corridor at least 1200mm wide in new buildings. An outward-opening or sliding door means a resident who falls against it can still be reached.
Full-height fixed screens look tidy but shut the carer out; half-height or hinged screens let staff reach the resident.
Contrast and dementia-friendly design
Approved Document M treats surfaces as visually contrasting when their light reflectance values differ by more than 30 points, and BS 8300-2:2018 carries the detail further. In practice, the WC seat, grab rails and basin edge should stand out clearly from the wall and floor behind them. A matt, plain, consistent floor colour avoids a dark strip or pattern reading as a step or a hole.
Grab rails, seats and support

Rails and seats should be positioned for how residents actually move, not where the wall happens to be clear. On our own installations, shower controls sit between 700 and 900mm of the seat, so a seated resident can adjust the water without standing and a carer can reach the controls too. Walls behind seats and rails must take the load, which is a question for the survey.
Questions that separate contractors
These six questions tend to separate a contractor who has worked in occupied care homes from one who has not.
1. Who leads the job, who is on site each day, and is the main installation subcontracted?
2. What is the wet PTV of the floor you are proposing, and does it run through the whole room?
3. Which TMVs will you fit, and will you commission them and give us the recorded settings?
4. Will you remove redundant pipework rather than cap it, and tell us exactly what has changed for our Legionella risk assessment?
5. How long will this room be out of use, and where will the nearest usable WC be every night?
6. Is the price fixed and written, and what does it exclude?
Answers to the last question are where quotes differ most. Strip-out, floor preparation, TMV commissioning and building control fees are the items most often missing from the cheaper price.
Running the works while residents live there
Work on one bathroom at a time wherever the building allows, and agree the order of rooms before the start date. Each affected resident should know which bathroom they will use in the meantime, and a usable WC should be close to the work area every night. For the planning in more detail, see our guide to refurbishing while the home stays open.
Agree in advance when noisy work will happen, away from medication rounds and mealtimes. Ask how the work area will be sealed from the corridor, which route waste will take out of the building, and how the area will be left each evening. Brief the contractor on your IPC arrangements and on what happens if there is an outbreak while they are on site. Water services that have been isolated need flushing before they return to use.
Fire routes stay clear and fire doors stay closed. Agree sign-in and the checks you require of anyone working in the home before day one, not on it. Name one contact on each side so messages do not get lost between shifts.
What good handover looks like
Handover is the point at which the home can show the room is safe to use and its records are up to date. A good handover includes:
- A walk-round with the contractor and a senior carer who bathes residents, testing the room as it will be used: the hoist through the door, a shower chair on the fall, the seat, the rails, the drain under full flow and the emergency alarm.
- TMV commissioning records with the set temperatures, and the outlet temperatures measured on the day.
- A note of all pipework removed or altered, so the Legionella risk assessment, written scheme and flushing records can be updated before first use.
- The floor manufacturer’s cleaning guidance, because the wrong product can leave a film that reduces slip resistance.
- Warranties, product manuals and any building control completion certificate, filed where your estates lead can find them.
- A date to come back. Problems with a wet room usually show up in the first few weeks of daily use, not on handover day.
We give a five-year installation warranty on our work, with manufacturers’ warranties on the products on top, and we come back to check how the room is working.
Honest summary
- Specify from the residents’ bathing and transfer needs, looking two to five years ahead.
- Agree the fall, the drain position, the floor’s wet PTV and the TMVs in writing.
- Measure the door and the room with a hoist, a shower chair and two staff in mind.
- A good handover leaves you with commissioning records, a pipework note and a date to review.
Planning a care home bathroom in the next twelve months? Lee (Hertfordshire, Bedfordshire and Buckinghamshire) or Charlie (Devon) will visit, look at the room with you, and give you one fixed, written price. Read more about how we work with care homes.
Frequently asked questions
How much does a care home bathroom refurbishment cost?
It depends mainly on the floor. A wet room needs a fall and a drain built into the floor, and timber and concrete floors behave very differently. Room size, door widening, the finishes and TMVs, relocated services and any building work are the other main drivers. We give one fixed, written price after a site visit. When comparing quotes, check whether strip-out, floor preparation and TMV commissioning are included.
How long will the bathroom be out of use?
Most of our bathroom installations take five working days, Monday to Friday. Larger jobs involving building work take longer, and you get a clear timeline before work starts. We work on one bathroom at a time and do not drag it out, and a usable WC is always available overnight.
What are the best ways to adapt a care home bathroom for older residents?
Start with how residents bathe and transfer, then remove the barriers that follow from it. For many homes that means a level access shower room or wet room with a slip-resistant floor throughout, TMVs, a fold-down seat and rails positioned for use, contrasting fittings and enough space for a hoist and two staff.
What are the CQC bathroom requirements for a care home, and which guidance applies?
CQC does not set a fixed bathroom specification. The regulatory starting points are Regulation 12 (infection prevention and control) and Regulation 15 (premises and equipment) of the 2014 Regulations. HSE guidance covers hot water, scalding and Legionella. Approved Document M Volume 2 and BS 8300-2:2018 cover access and contrast, and HBN 00-02 is a useful, non-mandatory benchmark for assisted shower room layouts.
Sources
- Health and Social Care Act 2008 (Regulated Activities) Regulations 2014, regulation 12: https://www.legislation.gov.uk/uksi/2014/2936/regulation/12
- Health and Social Care Act 2008 (Regulated Activities) Regulations 2014, regulation 15: https://www.legislation.gov.uk/uksi/2014/2936/regulation/15
- Care Quality Commission, “Regulation 15: Premises and equipment”: https://www.cqc.org.uk/guidance-regulation/providers/regulations-service-providers-and-managers/health-social-care-act/regulation-15
- Department of Health and Social Care, “Health and Social Care Act 2008: code of practice on the prevention and control of infections and related guidance”: https://www.gov.uk/government/publications/the-health-and-social-care-act-2008-code-of-practice-on-the-prevention-and-control-of-infections-and-related-guidance
- HSE, “Scalding and burning” (health and social care): https://www.hse.gov.uk/healthservices/scalding-burning.htm
- HSE, “Managing the risk from hot water and surfaces in health and social care” (HSIS6): https://www.hse.gov.uk/pubns/hsis6.pdf
- HSE, “Legionella and Legionnaires’ disease” (health and social care): https://www.hse.gov.uk/healthservices/legionella.htm
- HSE, “Assessing the slip resistance of flooring” (technical information sheet, UKSRG classification): https://www.hse.gov.uk/pubns/geis2.pdf
- NHS England, “Health Building Note 00-02: Sanitary spaces”: https://www.england.nhs.uk/publication/designing-sanitary-spaces-like-bathrooms-hbn-00-02/
- HM Government, “Approved Document M: Access to and use of buildings, Volume 2: Buildings other than dwellings”: https://www.gov.uk/government/publications/access-to-and-use-of-buildings-approved-document-m
- BSI, “BS 8300-2:2018 Design of an accessible and inclusive built environment. Buildings. Code of practice”: https://knowledge.bsigroup.com/products/design-of-an-accessible-and-inclusive-built-environment-buildings-code-of-practice
- The King’s Fund and University of Worcester, “Is your care home dementia friendly? EHE environmental assessment tool”: https://www.worc.ac.uk/about/academic-schools/school-of-health-and-wellbeing/health-and-wellbeing-research/association-for-dementia-studies/ads-consultancy/the-kings-fund-environmental-assessment-tools/home.aspx